Every site is different
The intended activation sequence can vary by zone, floor, stair, shaft, inlet, fan, damper, vent, fire-alarm input and manual override. The correct basis for a visit may include the original design information, later revisions and manufacturer requirements.
What functional testing records
A maintenance visit can record the accessible equipment inspected, the initiation used, the observed sequence, readings, defects, isolations, remedial requirements and the condition in which the system was left.
Where original design information is unavailable
The report should not automatically state that the original design, fire strategy or cause-and-effect sequence has been independently verified. Smokevent Pro uses scope wording that distinguishes recorded functional operation from specialist design verification.
The original cause-and-effect information, fire strategy and/or commissioning documentation was not made available for this attendance. Functional operation was tested within the scope recorded in this report. This report does not independently verify the original smoke-control design, fire strategy, cause-and-effect sequence or suitability of the system for the building.